The Setup
You have 3 projects to complete. Each project has 10 tasks that must be done in sequence (Task 1, then Task 2, etc.). Each task takes 2 weeks.
- P1 (High Value) - Earns $10,000/week once complete
- P2 (Medium Value) - Earns $8,000/week once complete
- P3 (Lower Value) - Earns $5,000/week once complete
The Three Scenarios
Ideal (9 resources)
Each project gets its own dedicated Blue, Yellow, and Green. All 3 projects finish at week 20 simultaneously. This is the dream, but requires 3x the staff!
Single-tasking (3 resources, focused)
One Blue, one Yellow, one Green - but they FOCUS on finishing P1 completely before starting P2, then P3. Projects finish at weeks 20, 28, 36.
Multitasking (3 resources, diluted)
Same 3 resources, but they switch between all projects constantly. Everyone waits, everything is delayed. Projects finish around weeks 48, 50, 52.
What to Watch For
Run each scenario and compare:
- When does each project finish?
- How much money is earned by week 60?
As you'll see, multitasking costs a fortune - yet it's how most businesses operate. Run the simulations to see why.